HomeMy WebLinkAboutRES 23-7408 (POLICE STATION IMPROVEMENTS)
Page 1 of 4 RES NO. 23-7408
CITY OF HERMOSA BEACH
RESOLUTION NO. 23-7408
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HERMOSA BEACH,
CALIFORNIA, APPROVING THE CONSTRUCTION OF CIP 696 POLICE
STATION IMPROVEMENTS PROJECT PURSUANT TO GOVERNMENT CODE
SECTION 830.6, SUSTAINING THE DETERMINATION OF NON-
RESPONSIVENESS AND NON-RESPONSIBILITY, AND ESTABLISHING A
PROJECT PAYMENT ACCOUNT
WHEREAS, The City solicited competitive bids for the Police Station
Improvements Project; and
WHEREAS, Bids were received and opened publicly on November 2, 2023,
and [R Dependable Const Inc.] was chosen as the lowest responsible bidder;
WHEREAS, There was another bidder (Esparza Development) that submitted
a lower bid than R Dependable Const Inc.; however after a bid protest, City staff
determined that this bid was non-responsive and that the bidder was not
responsible;
WHEREAS, The City Council, desires to confirm City staff’s determination and
award the construction contract to the lowest responsible bidder, [R Dependable
Const Inc.] for the Police Station Improvements Project.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF HERMOSA BEACH,
CALIFORNIA, DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. On November 2, 2023 the City received a total of five (5) bids
which are summarized below:
BIDDER BID AMOUNT
Esparza Development $ 136,000.00
R Dependable Const Inc. $ 148,790.00
Meyers Construction Co. $ 164,600.00
DocuSign Envelope ID: 930DD1E9-A1CB-41CB-806E-E4D2D521EC77
Page 2 of 4 RES NO. 23-7408
ENL Building Service Inc. $ 167,000.00
CTG Construction, Inc. DBA C.T. Georgiou
Painting Co $ 250,000.00
On November 13, 2023, the City received a formal bid protest from the second
apparent low bidder (R Dependable Const Inc) with respect to CIP 696 Police
Station Improvements Project. In pertinent, the bid protest noted that in the City’s
instruction to bidders, the bid documents required that the Contractor
demonstrate that it shall have a minimum of five (5) projects of similar type of
construction and magnitude with other public agencies within the past five (5)
years. Further, the bid protest pointed out that the bid by Esparza Development
listed only one (1) project that ended in 2016 (i.e., did not list a minimum of five
(5) projects of similar type of construction and magnitude with other public
agencies within the past five (5) years).
Per the Protest Procedures outlined in Section III of the Instruction to Bidders in the
Project Contract Documents, the bid protest was sent to all parties that may be
affected by the outcome of the protest. A deadline for submitting a response to
the bid protest was established for Wednesday November 22, 2023, at 12 p.m.
Esparza Development did not respond to the bid protest. As such, the City staff
recommends sustaining the protest, determining that the apparent low bid is
materially non-responsive as it did not list the required five (5) projects of similar
type of construction and magnitude with other public agencies within the past
five (5) years. Further, the lack of the required projects within the stated period of
time results in a determination that the bidder is non-responsible pursuant to Public
Contract Code § 1103 in that the bidder lacks the required experience to
satisfactorily perform the public works contract.
Thus, the City Council rejects the Esparza Development’s bid on the above bases
and awards the construction contract to the lowest responsible bidder, [R
Dependable Const Inc.] for the Police Station Improvements Project.
SECTION 2. The City Council wishes to obtain the immunities set forth in
Government Code § 830.6 with regards to the plans and construction of the
Project. The City Engineer finds that the plans are complete, and the Project may
be constructed.
SECTION 3. Design Immunity; Authorization
DocuSign Envelope ID: 930DD1E9-A1CB-41CB-806E-E4D2D521EC77
Page 3 of 4 RES NO. 23-7408
A. The design, plans and vendor proposal for the Project are
determined to be consistent with the City’s standards and are approved;
B. The design approval set forth in this Resolution occurred before
actual work on the Project construction commenced;
C. The approval granted by this Resolution conforms with the City’s
General Plan;
D. The City Engineer, or designee, is authorized to act on the City’s
behalf in approving any alterations or modifications of the design and plans
approved by this Resolution; and
E. The approval and authorization granted by this Resolution is intended
to avail the City of the immunities set forth in Government Code § 830.6.
SECTION 4. For purposes of the Contract Documents administering the
Project, the City establishes an account containing sufficient monies from the
current and following fiscal year budget to pay for the project. This Account is the
sole sources of funds available for the Construction Sum as defined in the
Contract Document administering the Project.
SECTION 5. The Project is exempt under the California Environmental
Quality Act (“CEQA”) pursuant to CEQA Guidelines section 15301 (Existing
Facilities). The proposed work is a minor alteration of existing public structures or
facilities involving negligible or no expansion of existing use. No exceptions to the
CEQA exemption apply.
SECTION 5. The City Clerk is directed to certify the adoption of this
Resolution.
SECTION 6. This Resolution will become effective immediately upon
adoption.
DocuSign Envelope ID: 930DD1E9-A1CB-41CB-806E-E4D2D521EC77
Page 4 of 4 RES NO. 23-7408
PASSED, APPROVED, and ADOPTED on this 12th day of December 2023.
Mayor Justin Massey
PRESIDENT of the City Council and MAYOR of the City of Hermosa Beach, CA
ATTEST: APPROVED AS TO FORM:
________________________________ ________________________________
Myra Maravilla, Patrick Donegan,
City Clerk City Attorney
DocuSign Envelope ID: 930DD1E9-A1CB-41CB-806E-E4D2D521EC77
State of California ) County of Los Angeles ) ss
City of Hermosa Beach )
December 18, 2023
Certification of Council Action
RESOLUTION NO. 23-7408
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HERMOSA BEACH, CALIFORNIA, APPROVING THE CONSTRUCTION OF CIP 696 POLICE STATION IMPROVEMENTS PROJECT PURSUANT TO
GOVERNMENT CODE SECTION 830.6, SUSTAINING THE DETERMINATION OF NON-RESPONSIVENESS AND NON-RESPONSIBILITY, AND ESTABLISHING A PROJECT PAYMENT ACCOUNT
I, Myra Maravilla, City Clerk of the City of Hermosa Beach do hereby certify that
the above and foregoing Resolution No. 23-7408 was duly approved and
adopted by the City Council of said City at its regular meeting thereof held on
the 12th day of December 2023 and passed by the following vote:
AYES: MAYOR MASSEY, MAYOR PRO TEMPORE FRANCOIS,
COUNCILMEMBERS SAEMANN, DETOY and JACKSON
NOES: NONE
ABSTAIN: NONE
ABSENT: NONE
________________________________
Myra Maravilla,
City Clerk
DocuSign Envelope ID: 930DD1E9-A1CB-41CB-806E-E4D2D521EC77